Construction of 01 MW Hydro Power Project at Juglote Sai Gilgit.
Hydropower Engineering
Solo Contractor
Project Overview
TOTAL PROJECT COST
Rs. 114.094 Million
TIMELINE / DURATION
5 Months (Jan-2019 to Jun-2019)
EMPLOYER / CLIENT
Water & Power Division Gilgit
Water & Power Department GB PWD Konodas Gilgit
CONTRACTOR ROLE
Independent Contractor (Solo)
Technical Execution Scope & Summary
The Construction of 01 MW Hydropower Project (HPP) at Juglote Sai involved the procurement and fitting of the penstock pipe, inclusive of all allied civil structures, pipe pillars, and anchor blocks. The project commenced in January 2019 and successfully concluded in June 2019, a...
Note: Detailed execution blueprints, drawings, and monthly reports are archived in the main corporate database.
Official Documentation & Certificates
Government of Gilgit-Baltistan Office of the Executive Engineer Water and Power Division Gilgit
Government of Gilgit-Baltistan Office of the Executive Engineer Water and Power Division GilgitGovernment of Gilgit-Baltistan Office of the Executive Engineer Water and Power Division Gilgit
Government of Gilgit-Baltistan Office of the Executive Engineer Water and Power Division GilgitRecommended Projects
Solo
Solo
JV-partner
Solo