Back to Projects




Project Details
Contract Package 05 B-Construction of Hospital, Shopping Center and Neighborhood Mosque in project colony in Thor Valley. Chilas District Diamer
Civil Construction
Solo Contractor
Project Overview
TOTAL PROJECT COST
Rs. 280.251 Million
TIMELINE / DURATION
5.0 Years (Jun-2011 to Mar-2016)
EMPLOYER / CLIENT
Water and Power Development Authority (WAPDA), Pakistan
Diamer Basha Dam Project WAPDA Chilas
CONTRACTOR ROLE
Independent Contractor (Solo)
Technical Execution Scope & Summary
Under Contract Package 05 B, a comprehensive initiative involved the construction of a Hospital, Shopping Center, and Neighborhood Mosque in the project colony situated in Thor Valley, Chilas District Diamer. This project commenced in June 2011 and concluded in March 2016, spanni...
Note: Detailed execution blueprints, drawings, and monthly reports are archived in the main corporate database.
Official Documentation & Certificates
Thor Colony Infrastructure Attachment 1
Thor Colony Infrastructure Attachment 2
Thor Colony Infrastructure Attachment 3