Design, Manufacture, Supply, Erection Testing and Commissioning of Electro-Mechanical Equipment of 14.4 MW Jhing Hydro Power Project District Muzaffarabad.

Hydropower Engineering
JV Partner (JV-partner)
Project Overview

TOTAL PROJECT COST

Rs. 786.05 Million

TIMELINE / DURATION

2 Years (Oct-2018 to May-2021)

EMPLOYER / CLIENT

AJK Power Development Organization (AJK PDO)

Upper Chapter Housing Society Muzaffarabad.

CONTRACTOR ROLE

Joint Venture Partner (JV-partner)

Technical Execution Scope & Summary

The 14.4 MW Jhing Hydropower Project marked a significant milestone through the Engineering, Procurement & Construction (EPC) Contract for the design, manufacturing, supply, erection, testing, and commissioning of Electro-Mechanical Works under IFB No.Jhing/001/2017. This venture...

Note: Detailed execution blueprints, drawings, and monthly reports are archived in the main corporate database.

Official Documentation & Certificates

Azad Jammu & Kashmir Power Development Organzation
Azad Jammu & Kashmir Power Development Organzation
Jhing Hydro Power Consultant - JHPC
Jhing Hydro Power Consultant - JHPC

Recommended Projects

Supply, Installation, Testing, Commissioning of Electro-Mechanical Component for 3.2 MW Khatai, 3.2 MW Sharian, 1.6 MW Leepa, 3.0 MW Qadirabad, 3.2 MW Rehra, and 600 KW Ranger Power Stations.
Solo
Supply, Installation, Testing, Commissioning of Electro-Mechanical Component for 3.2 MW Khatai, 3.2 MW Sharian, 1.6 MW Leepa, 3.0 MW Qadirabad, 3.2 MW Rehra, and 600 KW Ranger Power Stations.
Budget & Timeline

5.500 Million / 0.5 Years

Diamer Basha Dam project - Contract Package 09 Construction of 3.6 MW Hydro Power Project for Thor Colony Chilas Gilgit Baltistan, Pakistan.
Solo
Diamer Basha Dam project - Contract Package 09 Construction of 3.6 MW Hydro Power Project for Thor Colony Chilas Gilgit Baltistan, Pakistan.
Budget & Timeline

1283.48 Million / 3.5 Years

Construction of 01 MW Hydro Power Project at Juglote Sai Gilgit.
Solo
Construction of 01 MW Hydro Power Project at Juglote Sai Gilgit.
Budget & Timeline

114.094 Million / 5 Months

1.5 MW Hydel Power Project At Gulmuti PhII (Supply, Installation, Commissioning and Test Running Turbo Generating Sets).
Solo
1.5 MW Hydel Power Project At Gulmuti PhII (Supply, Installation, Commissioning and Test Running Turbo Generating Sets).
Budget & Timeline

84.89 Million / 3.5 Years